Installation preparation and adjustment of vibrating sieve

Preparation of vibrating sieve before installation

  1. Check the motor signs are consistent with the requirements;
  2. With 500 V megohmmeter insulation resistance measurement, the value of the stator winding should be dried, drying temperature can not exceed 120 ℃;
  3. Check the motor fasteners, beware of loose;
  4. Check the motor surface for damage, deformation;
  5. Check whether the flexible rotation, if abnormal, it should be excluded;
  6. Check the power, whether the lack of phase, and no-load operation for 5 minutes.

 

Rotary vibrating sieve installation and adjustment

  1. The equipment motor should be fastened on the mounting surface, the mounting surface must be smooth, smooth;
  2. The motor can be installed horizontally
  3. The motor lead with four-core rubber cable YZ-500V, then the power cord lead wire is not allowed to havebend, and fixed with vibration body;
  4. The motor should be reliably grounded, there are grounding devices in the motor, lead the end of a sign, you can also use the firm foot bolts grounding;
  5. Exciting force adjustment.